The Planning Commission has begun work to update Edina’s zoning ordinance. The goals of the zoning ordinance revisions are to bring it into compliance with the Comprehensive Plan, make the City’s development process more clear, consider a Planned Unit Development District ordinance to allow flexibility from standard zoning in exchange for strengthened City control over development, resolve the procedural issue of the Zoning Board of Appeals taking final action on large development projects requiring variances, and add performance standards.

The Planning Commission is forming a committee of the whole to recommend changes to the zoning ordinance. When a meeting is indicated in this process chart, it is intended that it be a meeting of the committee, not a meeting of the Commission. During the process, which is outlined below, there will be opportunities for the public to participate and offer comments and suggestions. Meetings of the Zoning Ordinance Update Committee (ZOUC) are open to the public. Time will be reserved for public comment at the end of each meeting’s agenda.

DOCUMENTS

Get Acrobat Reader You'll need version 3.01 or later of Adobe Acrobat Reader™ to view these documents.
Meeting Topics
Wetland Setback Download information on the discussion of Wetland Setback.
Variance Process Review Download information on the discussion of the Variance Process Review.
Tree Preservation Download information on the discussion of tree preservation.
Traffic/Parking Review Download information on the discussion of the Traffic/Parking Review.
Sustainable Design Download information on the discussion of Sustainable Design.
Staff Meeting(s) with Developers Download information on the discussion of Staff Meeting(s) with Developers
Role of Heritage Preservation Board Download information on the discussion of the role of the Heritage Preservation Board.
Role of Energy & Environment Commission Download information on the discussion of the Role of the Energy & Environment Commission.
Planned Unit Development (PUD) Download information on the discussion of Planned Unit Developments.
Public Hearings Download information on the discussion of Public Hearings.
Neighbors Download information on the discussion about the Requirement for Developers to Meet With Neighbors.
List of Conditions Download information on the discussion of List of Conditions Required by the City.
Driveway Width Download information on the discussion of Driveway Width.
 
Oct. 14, 2009 Community Input Session Documents
Summary Download a summary of key issues raised at the meeting.
PowerPoint Download the PowerPoint presentation given at the meeting.
Worksheets Download worksheets. Fill them in and return to the Planning Department!
Worksheets Download worksheets completed at the meeting.
Work Plan Download the work plan.
Meeting Minutes Download meeting minutes from the Sept. 9 meeting.
Notes and Summaries Download work session notes and summaries of key issues raised at the May 13, June 10, July 29 and Aug. 12 meetings.
Meeting Schedule Download the ZOUC meeting schedule.
Proposed Table of Contents Download a proposed table of contents for the Zoning Ordinance and a draft flow chart of the development review process.
   

PROCESS

Stage

Task

Description

Assessment and Information Gathering

 

1

Compile a list of modifications required to bring zoning ordinance into conformance with Comprehensive Plan; identify, from a Planning Commission perspective, other areas of the zoning ordinance requiring revision or update; analyze the development review process to identify deficiencies from a City perspective

Involvement: Planning Commission

Timing: This task has been largely accomplished, but may need to be more definitively memorialized.

Arrowing indicating where the ZOUC is at with the process. 

2

Engage representatives from various segments of the development community in a forum aimed at gaining their insights into the city’s development review process and zoning requirements

Involvement: Planning Commission, development community representatives (retail, office, industrial, multi-family residential, single family residential, and institutional)

Timing: Zoning Ordinance Update Committee (ZOUC) meeting on May 13, 2009

 

3

Invite other City commissions to ZOUC meeting(s) to identify directions for zoning revisions consistent with their goals and the City’s regulatory needs, and to review other directions under consideration by each commission

Involvement: Planning Commission, other commissions

Timing: Beginning with ZOUC meeting on June 10, 2009, and continuing through August 2009

 

4

Conduct a community meeting to share the process of updating the zoning ordinance with the Edina community, to solicit input regarding anticipated changes or areas of potential change, and seek local insights into City development review process and zoning requirements

Involvement: Planning Commission, general public (residents, business owners, property owners)

Timing: September 2009

 

5

Conduct a workshop with City Council to review input gathered from Stage 1, and to solicit further input regarding the City’s development review process and zoning requirements

Involvement: Planning Commission, City Council

Formulation of Potential Revisions

 

6

Develop draft revisions required to align the zoning ordinance with the Comprehensive Plan

Involvement: Planning Commission

Timing: Complete by Oct. 14, 2009

 

7

Develop draft revisions or recommend alternatives to the zoning ordinances focusing on performance standards; form subcommittees to develop recommendations for revisions or additions for areas of the ordinance where direct input from other commissions provides a greater degree of specificity or insight for the proposed revision

Involvement: Planning Commission, other commissions

Timing: Complete by Nov. 11, 2009

 

8

Frame a development review process that addresses deficiencies identified during the first stage of the zoning ordinance update

Involvement: Planning Commission

Timing: Complete by Jan. 13, 2010

 

9

Formulate draft recommendations for changes to the zoning ordinance and development review process

Involvement: Planning Commission

Timing: Complete by Feb. 9, 2010

 

10

Conduct a workshop with City Council to review input offered during Stage 2 and draft recommendations for changes to the zoning ordinance and development review process

Involvement: Planning Commission, City Council

Timing: Late February 2010

Evaluation of Potential Revisions

 

11

Conduct a community meeting to share draft recommendations for changes to the zoning ordinance with the Edina community and the development review process

Involvement: Planning Commission, general public (residents, business owners, property owners)

Timing: Late March 2010

 

12

Invite development community representatives to a forum to review the draft  recommendations of changes to the zoning ordinance and the development review process

Involvement: Planning Commission, development community representatives (retail, office, industrial, multi-family residential, single family residential, and institutional)

Timing: ZOUC meeting on April 13, 2010

 

13

Conduct a workshop(s) with other City commissions to review the draft recommendations for changes to the zoning ordinance and the development review process

Involvement: Planning Commission, other commissions

Timing: ZOUC meeting on May 12, 2010

 

14

Prepare recommendations for changes to the zoning ordinance and development review process based on input from community, development community representatives, City Council, and other city commissions

Involvement: Planning Commission

Timing: ZOUC meeting on June 9, 2010

 

15

Conduct a workshop with City Council to informally evaluate the potential revisions to the development review process and zoning ordinances

Involvement: Planning Commission, City Council

Timing: Late June 2010

Confirmation

 

16

Distribute recommendations for changes to the zoning ordinances and the development review process to other city commissions; request a formal review and recommendation by each reviewing commission

Involvement: Planning Commission, other commissions

Timing: July and August 2010

 

17

Develop final recommendations for changes to the zoning ordinances and the development review process based on the formal review by other city commissions

Involvement: Planning Commission

Timing: ZOUC meeting on Sept. 8, 2010

 

18

Conduct regulatory hearings at the Planning Commission and City Council to adopt the recommended changes to the zoning ordinances and development review process

Involvement: Planning Commission, City Council

Timing: Early November 2010

Assumptions and Notes

 

 

The timeline indicated should be considered an approximate schedule, and is subject to change to accommodate additional input, information gathering, and exploration of potential revisions.  The schedule will be updated as final dates are identified.

 

 

As the process for updating the City’s zoning ordinance proceeds, the ZOUC may determine that further input is required to fully understand the issues and potential directions for change, and that additional opportunities for gaining input and sharing directions for potential changes will be required.  The process will be updated as the need for additional meetings, workshops, or other input or review opportunities are identified.